UNRA On the Spot Over Abandoned Road Project

1254 Views Kabale, Western Region, Uganda

In short
Boaz Kazibwe, the Kabale Area Manager Uganda National Roads Authority, says the contractor disappeared without notice.

Uganda National Roads Authority-UNRA has come under fire from Kabale residents for abandoning the rehabilitation of Muhanga-Kyogo-Kamwezi road. The 20 kilometer road stretch connects Uganda to Rwanda via Rwamatunguru boarder. 

The road also connects Kyabuhangwa and Kyogo parishes to Ntungamo-Kabale road via Muhanga Town council. Residents use the same road to access health services at Kyogo Health three in Kyogo Parish. In August 2015, UNRA contracted Ms Summit Project Limited to rehabilitate the road. 

However, work didn't start until February 2016. According to the plan, the contractor was expected to expand the road, put first class murram and culverts as well as work on the drainage channel.  However, local leaders and residents claim that the contractor only worked for three days and disappeared. 

They are demanding an explanation from UNRA why the contractor abandoned the works, yet the road is in a very bad shape. Pamela Kyaikunda, a resident of Kyabuhangwa parish, says she only saw the road workers busy for three days before they disappeared without any trace.
 
 
According to Kyarikunda, she is finding difficulty to transport her produce to Rwamatunguru boarder Market because of the poor state of the road. Kyarikunda says she is currently stuck with five bags of unsold sorghum due to the bad road. 

James Mugarura, a resident of Kyogo parish says that patients in need of emergency medical attention also find it difficult to access Kyogo health center III. He hopes district authorities especially the office of the Kabale Resident District Commissioner will investigate the stalled road works.
 

//Cue in; "Twiine ne'nkuto ya…..
Cue out;……..kubi munonga"//

Rukiga


Cue in:
Cue out:


Tedson Niwagaba, the Kamwezi Sub County LC III Chairperson says the community was happy with the road works even when some of them lost property. Niwagaba says as sub county leaders they don't know why the contractor abandoned work.
 

//Cue in: "it is becoming……
Cue out …..relevant offices"//

 
Boaz Kazibwe, the Kabale Area Manager Uganda National Roads Authority, says the contractor disappeared without notice. He however, says plans are underway by the Authority to fix the road before the end of this month. 

 

Tagged with: unra road works

About the author

Samuel Amanya
Samuel Amanya is the Kigezi Region URN bureau chief. Kabale, Kisoro, Kanungu and Rukungiri districts fall under his docket. Samuel Amanya has been a Uganda Radio Network reporter since August 2016. Before becoming a URN staff reporter, Amanya had written for the network for several years as a freelancer.


Amanya was also a Voice of Kigezi reporter from 2011 to 2016.


A journalism graduate from African College of Commerce Kabale, Amanya values his independence. Amanya says URN is a home for his talent because it lets him explore his journalistic interests without limits.

Amanya is fascinated by the crime beat and some of his best stories have come out of that interest. Amanya says he aims to be all round beat reporter.